Swanton announces Garfield Ave. traffic restrictions


The contractor for Project 8 & 9 sewer separation has notified the Village of Swanton of their intent to begin work three weeks early, tentatively on March 28, weather contingent.

Road work will take place in four phases and span until summer 2022. Complete details and updates on timelines will be posted on the Village’s website throughout the remainder of the project.

Phase 1 will center on W. Garfield Avenue, between Browning and Munson roads. The work will include roadway excavation, installation of stone base and concrete curbs. During this phase there will be no parking permitted on W. Garfield Avenue, between Browning and Munson roads.

West Garfield Avenue will be one way traffic, westbound from Elton’s Parkway to Browning and closed from Browning to Munson. West Garfield will remain two way between Elton’s Parkway and Main Street.